The tunnel runs north to south beneath the park for 2,430 m: a new 1,590 m section joined to an existing 840 m one, with three lanes each way plus an emergency lane. The Foundation announced completion on 28 February 2024 and it opened to vehicles the next day, the first of the park's tunnel-and-bridge projects.
Key facts
| Total length |
2,430 m
King Salman Park Founda…Feb 2024King Salman Park Founda…Feb 2024Al Eqtisadiah (SPA)Feb 2024
New and existing sections combined, Foundation announcement of 28 Feb 2024 · as of Feb 2024
|
|---|---|
| New section |
1,590 m
King Salman Park Founda…Feb 2024Al Eqtisadiah (SPA)Feb 2024
Newly built part · as of Feb 2024
|
| Existing section |
840 m
King Salman Park Founda…Feb 2024Al Eqtisadiah (SPA)Feb 2024
Pre-existing tunnel joined to the new one · as of Feb 2024
|
Traffic goes under, people stay on top
The point of the tunnels is simple: keep busy roads out of the park. The Foundation says the tunnels isolate traffic, limit pollution and noise leaking into the park and increase the total green area.
What it is
The Abu Bakr Al-Siddiq Road tunnel crosses the park north to south over 2,430 m. According to the Foundation's announcement a new 1,590 m section was joined to an existing 840 m tunnel. It has three lanes in each direction plus an emergency lane, modern traffic management and safety systems, and, per one report, a water-mist system. Its interior uses colour gradations that evoke earth layers and Riyadh's rock formations, in line with the Salmani architecture language.
Timeline
Works began in the third quarter of 2021 under the SAR 3.847 billion contracts for site preparation, tunnels and bridges that Arab News reported in September 2021. The Foundation announced completion on 28 February 2024, and vehicles were allowed from 29 February. It was the first completed component since works began.
How long is "longest"?
Some coverage calls it one of the longest tunnels in the Middle East. We have not found a ranking source, so we leave the claim out.
Where it stands
Completed and in use as a road. Our map position is the midpoint of the portals as drawn in OpenStreetMap, so it is approximate.
Timeline
First major contracts: about USD 1bn (SAR 3.85bn)
The Foundation awarded SAR 3.847bn of work for site preparation, tunnels and bridges on Abu Bakr Al-Siddiq and Al Urubah roads, and groundwork for the Royal Arts Complex. This marks the real start of construction.
King Salman Park Founda…Jan 2022Arab NewsSep 2021Abu Bakr Al-Siddiq tunnel completed and opened to traffic
The Foundation announced the 2,430 metre tunnel complete on 28 February 2024, with vehicles using it from 29 February. It was the first of the park's bridge-and-tunnel works to finish.
Al Eqtisadiah (SPA)Feb 2024SUSTGFeb 2024News
- 28 Feb 2024 Abu Bakr Al-Siddiq tunnel completed Al Eqtisadiah (SPA)SUSTG
Sources
- OSM way 245588756 Abi Bakr Al Siddiq Tunnel (© OpenStreetMap contributors, ODbL) · OpenStreetMap contributors, 12 Nov 2026
- (Arabic version) Opening of Abu Bakr Al-Siddiq Tunnel · King Salman Park Foundation, 28 Feb 2024
- Opening of Abu Bakr Al-Siddiq Tunnel · King Salman Park Foundation, 28 Feb 2024
- افتتاح نفق طريق أبي بكر الصديق في حديقة الملك سلمان لتحسين التدفق المروري في الرياض · Al Eqtisadiah (SPA), 28 Feb 2024
- King Salman Park awards $1bn construction contracts · Arab News, 22 Sep 2021
- King Salman Park inaugurates tunnel · SUSTG, 29 Feb 2024